1 — Purpose
Implement a practical, school-owned AI governance system covering policy, privacy, safeguarding alignment, stakeholder training, pilot deployment, and ongoing governance cadence.
2 — Objectives
By project close, the Client will have:
- Living AI Policy v1.0 (online, versioned, school-owned)
- Named AI Policy Owner + Governance Panel
- Stakeholder training delivered (students, teachers, parents, admin, IT/compliance)
- Pilot deployment evidence + KPI baseline
- Incident response and policy update workflow with SLAs
3 — Scope of Work
Phase 1 — Weeks 1–2
Discovery & Baseline
- Readiness assessment (15 dimensions)
- AI tool inventory (formal + informal use)
- Stakeholder sentiment and fear mapping
- DPO/compliance alignment briefing
Deliverables
- Baseline report
- Risk register
- Values/fear map (aggregated)
Phase 2 — Weeks 3–5
Policy Sprint
- Draft + review Living AI Policy v1.0
- AI Tool Approval Checklist
- DPIA Trigger Checklist
- Policy Incident Register template
- Governance decision-rights matrix
Deliverables
- Policy Pack v1.0
- Governance model + version-control protocol
Phase 3 — Weeks 6–7
Onsite Training & Enablement
- Student activities (K–1, 2–5, 6–8, 9–12)
- Teacher practical workshops
- Parent information session
- Admin/IT governance workshop
- Leadership/board briefing
Deliverables
- Training completions log
- Activity map + facilitator guides
- Communications templates
Phase 4 — Weeks 8–10
Pilot Deployment
- Run approval workflow on at least 2 tools
- Activate incident logging process
- Equity audit for student-facing tools
- KPI dashboard baseline population
Deliverables
- Pilot report
- Policy refinements (v1.x)
Phase 5 — Weeks 11–12
Institutionalization
- Governance calendar for Year 1
- Board/governor outcome briefing
- 90-day post-implementation checkpoint setup
- Year 2/3 progression plan kickoff
Deliverables
- Operating cadence pack
- Handover + ownership transfer checklist
4 — Internal Capacity Requirements (Client Responsibilities)
- Appoint AI Policy Owner (0.1–0.2 FTE during 12-week period)
- Weekly leadership checkpoint (30 minutes)
- Workshop release time for staff (minimum 2 × 90-minute blocks)
- DPO/IT/legal review windows within agreed timeline
- Parent session communications support
5 — Out of Scope
- Legal advice / legal representation
- Tool procurement negotiation
- Full technical deployment/configuration of vendor platforms
- Bespoke curriculum design beyond included activity library
6 — Timeline & Milestones
| Milestone |
Target |
Description |
| M1 |
End Week 2 |
Baseline complete |
| M2 |
End Week 5 |
Policy v1.0 draft complete |
| M3 |
End Week 7 |
Training block complete |
| M4 |
End Week 10 |
Pilot evidence complete |
| M5 |
End Week 12 |
Final handover + board briefing |
7 — Acceptance Criteria
- Living Policy v1.0 is published
- Governance owner and panel are named
- Training completion logs submitted
- Pilot report + KPI baseline delivered
- Final review meeting completed
8 — Fees & Payment Terms
- Total fee: [£ / € / $ Amount — to be confirmed at contract signature]
- Payment schedule: 40% at signature | 40% at Phase 3 completion | 20% at final handover
- Travel/on-site expenses: [Included/excluded — confirm cap at contract signature]
9 — Change Control
Any scope changes require a written change order defining: additional deliverables, timeline changes, fee adjustments, and approval signatures from both parties before work commences.
10 — Data Protection, Confidentiality, and Legal Notice
Legal Notice: Governance templates and all deliverables produced under this engagement are operational implementation supports. They do not constitute legal advice and should not be relied upon as such. The Client retains independent legal responsibility for compliance with applicable law.
- Client owns all final policy/governance artifacts upon final payment.
- Provider handles all data per contract terms and applicable regulation.
- Confidentiality obligations survive project completion.
11 — Success Markers (First 90 Days)
- Policy published at school-owned URL
- Governance panel active and meeting on cadence
- ≥80% staff complete role-based training
- Incident register workflow active
- At least 2 AI tools evaluated through the formal approval framework